![]() |
Gregory Construction 30 Ton Low Profile Twinlift Fan replacement job at Noranda Aluminum near New Madrid, Missouri utlized Twinlift's double boom design to provide two picking points for more control over the bulky load. Twinlift's compact size makes it a great tool for use in congested environments. |
![]() |
Reed Machinery Movers Industrial Trailer Injection unit (wt. 115,000 lb) for a 1,780 ton molding machine being transported into location at Sunset Corp. (shown being towed by a Twinlift) |
![]()
|
Sheedy Drayage Co. Model 48A Installation of 640,000 lb electric generator at Los Medanos Energy Center. |
![]() ![]() |
Freight Wings Pvt. Ltd. Utilizing a Lift Systems 500 ton Power Tower, a 300 metric ton generator was raised to a height of 14 meters and placed on its foundation in a power plant in India. |
|
J.E. Oswalt & Sons Two 500 ton Power Towers lifted this 365 ft. 748 ton bridge from a barge and traveled over into position on the pedestal. |
![]() |
Shell Oil. Co. Mobilift M10 model built for Shell Oil Co.'s Mars oil rig, the deepest operating oil rig in the world. Lift Systems built the lift to meet special weight, size, and hazardous conditions requirements. It was used to place and remove the 12,000 pound running tool in the drill string, the main component of the oil rig and the part supported by the tower in the middle of the platform. U.L. certified. |
|
Gardner Contracting Company 500 Ton Power Tower with Model 48A Using this combination allowed for 900 ton picking capacity in the top stage. |
|
American Heavy Rigging & Hauling Co. Lift Systems' 24PT500L unloading one large vessel (23' in diameter by 60' long weighing 205 tons). Two smaller vessels were also unloaded. This system was also used to unload 30 vessels (the heaviest = 360 ton) for a major coal gasification project. |
![]() |
J.E. Oswalt & Sons Lift Systems' Power Towers have the stability and strength necessary for bridge work. |
|
Glass on a Fast Track Mini jacks put to work in Canadian biosphere It wasn't that the 4-inch-thick glass plates were that heavy, or even that the placement was difficult. The floor was the problem. "It just couldn't support very much weight" says Jean Lesage, Mega Lift Canada, "because the sensitive velodrome floor could only support 8,000 lbs., the simple possibility of using a crane or forklift was ruled out." |
|
The problem facing general contractor Baillargeon Express, of Montreal, Quebec,
was how to move $750,000 worth of Japanese manufactured glass plates to a beluga whale pool and beaver
pond, on a narrow elevated track system that turned, twisted and even descended.
Their answer was to call Mega Lift Canada, Inc., St. Therese, Quebec.
The solution was to build a track system and use mini jacks
to lift up the 4-inch-thick glass plates for the beaver pond and beluga whale pool. After a 15-minute
journey down the tracks, the mini jacks arrive at the beluga whale pool. At this point, the glass
plates are lowered and installed on the tank. The mini jacks were the only system that the consulting
firm, Janin Engineering of Canada, would approve for the job.
* Glass on a Fast Track story is attributed to Lift Equipment Magazine. |
Beck and Pollitzer Engineering Ltd.- 48A
![]() |
First the main machine casting is off loaded from the transporter into the factory. |
![]() |
Then the casting is stood up in a vertical position to be lowered into the pit. |
![]() |
Finally the 40 Tonne machining heads are lowered to the main casting. |